On 21 Feb 2010, continued with removing the starboard side propeller. We encountered difficulties in removing the propellers. Concurrently another team was doing the installation of new padeyes, cropping and renewing new bow metal fender pipe and installing newly refurbished bulwark piece with new wordings on it. Variation order incurred. The portside propeller’s shaft being pulled out partially in the afternoon. Jobs of loosening the starboard propeller were carried out until 1830H to no avail. Call it a day at 1930H after securing all the tools and working equipment. High tide did not raise until the skeg level of the vessel.
On 22 Feb 2010, with crane in location, we managed to move out both shafts and propellers to be send to workshop for their refurbishment process. Before doing that, with both shafts being partially pulled out, the clearance had been taken. Both propellers will be refurbish back into shape and static balancing will be carried out for both the propellers. Prop shaft will be remetalled and machined back to shape. Starboard side prop shaft found to be not straight and coldstraigtening process will be carried out to straighten it. Other jobs being carried out concurrently. Cropped and remove aft plate of port and starboard side. Deck cracks being rectified. Relocation of ship’s bell being carried out as well.
On the 23rd Feb, jobs being carried out were such as replacing all the manholes gaskets, removing ship side valves to be brought back for servicing and cleaning in the workshop. The propeller’s shaft, propellers and rudder were carried back to workshop for rectification works. Both propeller’s shaft had grooved for about 2mm. The propeller’s shaft were then being remetalled and machined back to size and stbd prop shaft had to be coldstraigthen. Dye penetration test was carried out at the keyway of the propeller’s shaft to make sure there’s no cracks in it. As for the rudders, heat fairing jobs being carried out for the starboard rudder as the upper plate was slightly dented. Both rudders were sand blasted and then being painted with undercoat and anti fouling paint. Each rudder was fixed with 2x zinc anodes of size 6B. The propellers’ blade (tips) were being brazed back to normal and balanced. Concurrently, all body works being carried out towards the end of the week.
On 1st Mac 2010, works of installation began. After installing new padeyes, installation of new chain holder for the tyres fender being carried out. Concurrently jobs of installing propeller’s shaft with new forward and aft cutless bearings also being carried out. With both the propeller’s shaft in, new tailshaft clearance was taken. Installation of new zinc anodes was also carried out as well. Ship side valves being fixed back with new gasket as well. Fixing the propellers were carried out afternoon and by the evening, both propellers were but without tightening the nuts as by then, the tide was coming in fast.
On 2nd Mac 2010, works started with tightening the propeller’s nuts. After that had been done, rudders were being lowered down via crane and being fixed too. New rudder’s clearance reading was taken. Jobs of tightening all the internal nuts for the forward cutless bearings (stern bush) were carried out in the engine room. This was to ensure that water will not flood the whole engine room and resulting the ship to sink. All ship side valves were made sure tighten. A 2 round checks for the ship side valves were carried out with the Chief Engineer and 2nd Engineer. 1x SCM surveyor came down for checking of all the vital parts that need to be sure.
On 4th Mac 2010, the ship was downslipped at around 1930H. Both gensets were activated to supply electricity for the ship on that night. Minor leakage was found on the propeller’s shaft packing glen for cooling water inlet. Wrapped both the area with clothes to minimise the water entry rate and called it a day as rectification jobs need to be done when the tide was low.
On 5th Mac 2010, jobs of rectifying the leakages being carried out. We found that leakages also occurred on the stern bush joints as initially the chief engineer told us not to fix gasket for that part. Removed the flanged cutless bearings and gaskets were fabricated as fast as possible to be fixed before the next high tide. The next day, both main engines being powered up but the starboard M/E didn’t activate. Chief Engineer reported this defect to owner’s rep and once again we were requested to rectify this problem together to fix back the gasket. Jobs being carried out at 2300H until 0630H 7 Mac 2010. All problems solved by then and the ship is ready for operation.
Overall test with the ship’s chief engineer was satisfactory and all found to be back to normal. Service reports being signed by the Master and our job is done.Bon Voyage. Now is time to become Ahlong and collect money from the owner! cipet.






























5 comments:
money collect boi? Haha
half half only
Sorry for my bad english. Thank you so much for your good post. Your post helped me in my college assignment, If you can provide me more details please email me.
i'm new... expectancy to brief approximately more oftentimes!
ha, I am going to try out my thought, your post bring me some good ideas, it's truly amazing, thanks.
- Murk
Post a Comment